HomeNews Construction of new Cambridge North Station delivered successfully

Construction of new Cambridge North Station delivered successfully

Recent

Work on the new Cambridge North Station has recently been completed, for Network Rail. The station’s first commuter services began on Monday 22 May. Located next to Cambridge science and business parks, and the A14 and A10, the new station is anticipated to handle 3,000 passenger journeys a day. 

Oxford station

Ground improvements

With a 4,843ft², footprint, Cambridge North features three platforms, along with parking for 450 cars and 1,000 bicycles. It has also been fitted with solar panels, providing up to 10 per cent of the station's power requirements. The original platform design called for ground improvements due to poor conditions. The team used a lightweight polystyrene backfill which required minimal ground preparation. This improved installation times, reduced the amount of possessions required and reduced the overall cost of the station.

Rail systems work

VolkerFitzpatrick began construction in 2015, starting with the realignment of the underused Chesterton sidings which opened up the brownfield site for development. Over the two-year lifespan of the project, it has taken months of meticulous planning, 700,000 hours of labour and 11 successful possessions to build the station on the operational West Anglia Main Line.

 

VolkerRail delivered the rail systems work for the station, along with associated remodelling work of the old Chesterton sidings yard, as part of the CP5 Multifunctional Framework in Anglia.

+